Skip to content
Case study · Kitchen remodels

Holly Springs kitchen and mudroom

Taking out a bearing wall in a lived-in house, on a fixed price and an 11-week schedule.

Year
2025
Time on site
11 weeks
Home
2004 two-story, 2,800 sq ft
Scope
Kitchen, mudroom, laundry move
Price
$86,000 fixed; one $1,450 change order
Before and after

See the difference.

One open room from the kitchen to the back windows. Shoes and bags stay in the mudroom.

  • Holly Springs, NC
  • 2025
  • Kitchen remodels
Before: the old kitchen with dated oak cabinets and a closed-in layoutBefore
After: the same kitchen opened up, with white cabinets and a long marble islandAfter
Holly Springs kitchen and mudroom
The job

What we found. What we did.

  1. Problem

    A 2004 kitchen closed off from the family room, with nowhere to drop bags and shoes. The family of five came in through the garage into a pile.

  2. Approach

    We took out a bearing wall with a flush beam, moved the sink to an island and turned a laundry closet into a mudroom with lockers. Laundry went upstairs.

  3. Result

    One open room from the kitchen to the back windows. Shoes and bags stay in the mudroom.

How the job went

Inside the job.

Taking out a bearing wall in a lived-in house, on a fixed price and an 11-week schedule.

The wall

The wall between the kitchen and family room carried the second floor. An engineer sized a flush LVL beam so the ceiling stays flat. We shored both sides and set it in one day.

The mudroom

The old laundry closet became a mudroom with five lockers, a bench and a tile floor that takes wet boots. The washer and dryer moved to a new room upstairs.

Week by week

  1. Weeks 1–2

    Dust walls, demo, temporary kitchen

  2. Week 3

    Beam day; framing inspection

  3. Weeks 4–5

    Plumbing, electrical and HVAC rough-in

  4. Weeks 6–7

    Drywall, paint primer, mudroom tile

  5. Weeks 8–9

    Cabinets, counters templated and set

  6. Weeks 10–11

    Backsplash, fixtures, final inspection, punch list

What we would tell the next client

  1. Pick appliances before the cabinet order, not after.
  2. Plan where the fridge goes during the build.
  3. Ask for photos of the walls before drywall. You will want them later.

From the client

“Every Friday we got an email with what got done, what was next and photos. We never once had to chase anyone.”

Jen W. · Holly Springs, NCGoogle · Nov 2025
Free quote

Get a quote like this.

Planning kitchen remodels? Tell us about the job and you hear back within one business day.